Traffic interchange at km 19+500 of «Perm Ust-Kachka» automobile road at the approach to Bolshoye Savino Airport Terminal

DESCRIPTION:
This remarkable site is located in the Perm municipal district of the Perm Territory at the section km 19+301 – km 20+023 of the automobile road «Perm — Ust-Kachka.» Design documentation for construction of traffic interchange on the highway «Perm — Ust-Kachka» with two levels crossing (approach) with junction location at the same level (approach, exit) was developed for providing access to the new terminal. Highway «Perm Ust-Kachka» is designed per 4 lanes.  Single-lane left-turn traffic interchange ramp with traffic flow movement design speed of 40km/h is intended for improvement of the main passenger traffic from the city of Perm. Carriageway width is conceived as 5.5m.
  • Flyover schema — 2х(24х3) m
  • Elevated road length — 146.175 m
  • Viaduct schema — 45+57+45.195 m
  • Overpass bridge length — 153.72 m
  • Retaining wall — 110.64m
  • Carriageway dimension — Г-7.5+2Т-0.75 m
  • Total weight of steel (decks) — 281.12 t
  • Deck RC slab — 347 m³
  • Entire volume of RC — 3,638.86 m³
SCOPE OF WORKS:
  • Design of main structures (design and work documentation)
  • Development of Construction Technology
  • SAC&D design (design and work documentation)
 CLIENT:
Regional State-Financed Institution «Department of Automobile Roads and Transport» of the Perm Territory
GENERAL CONTRACTOR:
Design and Construction Company Avtomost
DESIGN PERIOD:
  • Design documentation – 2014 — 2015
  • Work documentation – 2015
 CONSTRUCTION PERIOD:
2017