Highway flyovers on the highway Airport -Turkmenbashi road — National tourist zone «Avaza»

LOT No.1

DESCRPTION

Viaduct of 400m long within motorway Turkmenbashi Airport – national tourist resort «Avaza».

Total structures were designed with consideration for maximum seismic activity of 9 points and more.

Location of the viaduct was conceived for transportation convenience within city districts for the comfort of speedy Turkmenbashi Airport approach as well as to national tourist resort «Avaza» together with designed two independent lanes of cozy highway toward Turkmenbashi Town with the following basic features:

  • deck – solid RC structure of customized design
  • height of the structure – 1.4m
  • deck schema – 3х32+4х32+4х32m
  • total length – 1,527.84m
  • viaduct length – 400m
  • total length of 11 Exits – 3,800m
  • entire area – 51,780m²
  • total area of 11 Exits – 60,692m²
  • carriageway clearance — Г – 14.25+14.25
  • calculated live loads – А-14, НК-100

LOT No.2

DESCRPTION

Design and construction of the motorway bridge (flyover) with total length of 1,300 m within Turkmenbashi Airport approach toward national tourist resort «Avaza». The above-mentioned viaduct is located within North-West part of speed Turkmenbashi Highway Airport approach completed as a shortcut to national tourist resort «Avaza».

 

STRUCTURES WITHIN HIGHWAY

Flyover

  • continuous composite RC deck structure
  • schema — 30×42m
  • total length – 1,300m
  • flyover width between barriers – 36.3m
  • entire area – 47,190m²

Approaches to viaduct

  • approaches total length – 650m
  • carriageway clearance – 28.5m
  • area of approaches – 23,595m²
SCOPE OF WORKS

«Project Documentation» Stage

General Design function fulfillment

«Work Documentation» Stage

  • general design
  • total main structures design
  • SAC&D design
  • technical supervision
  • Federal Expertise passing
CLIENT

Department of construction in Ashkhabad City

GENERAL CONTRACTOR

ZAO «Vozrozhdenie»

DESIGN STAGE

«Design Documentation» Stage

2009 – 2010

«Work Documentation» Stage

2009 – 2011

CONSTRUCTION STAGE

2010 – 2011